Spending to save
Varian wind turbine
Cost: $8 million
Operational: December 2012
Size: 2.5 megawatts; 492 feet high from base to tip of blade
Electricity generated: Will power one-third of Varian’s Gloucester plant
Estimated savings per year: $1 million
Gloucester Engineering wind turbines (2)
Cost: $12 million
Operational: December 2012
Size: Each is 2 megawatts; 400 feet high from base to tip of blade
Electricity generated: Will power the Gloucester’s municipal buildings, including: City Hall; Gloucester High School; O’Maley Middle School; Beeman Memorial, East Gloucester, Plum Cove, Veterans’ Memorial, and West Parish elementary schools; Dorothy Talbot Rink; Office of Veterans’ Services; sewer treatment plant; police station; four fire stations; Sawyer Free Library
Estimated savings per year: $470,000
SOURCES: Varian and City of Gloucester