February 27, 1960: This is a view of the font end of the tunnel shield. A total of 134,000 cubic yards of material had to be excavated to complete the bore under the harbor. Sandhogs, from Boston Local 88, working 24 hours a day, six days a week, moved the excavation shield ahead an average of 16 feet per day.